Crews will perform road resurfacing, patching and pipe work in the area. Crews will also be building crossovers on the highway just north of the Sugar Creek bridge. A second crossover will be built just south of the I-74 overpass to direct traffic into the southbound lane on U.S. 231.
INDOT says a second phase of the project will switch traffic to the northbound lane while construction takes place on the southbound lane. And the third phase will switch traffic to its original pattern with one lane in each direction closed,