LEBANON, Ind. — Aerial photos taken Saturday, Nov. 21, show two of Boone County’s largest construction projects at different stages. At Eli Lilly and Co.’s manufacturing campus, multistory buildings rise beyond rows of parked vehicles and a large pond. At Meta’s data center site, graded ground, construction pads and access roads stretch across a broad area bordered by farm fields.

Both projects are part of Lebanon’s LEAP Research and Innovation District, but they serve different purposes and are on separate schedules. Lilly opened the first of its three planned Lebanon facilities in May and expects its active pharmaceutical ingredient plant to open in 2027. Meta broke ground in February on a data center campus representing more than $10 billion in planned investment and expects its first buildings to come online in late 2027.

Lilly has opened its first Lebanon facility
Lilly Lebanon Advanced Therapies opened May 6 as the company’s first facility dedicated to manufacturing genetic medicines. The same day, Lilly announced an additional $4.5 billion investment across two of its three Lebanon sites: Advanced Therapies and the active pharmaceutical ingredient plant, known as Lebanon API. Lilly plans to use the API site to make ingredients for medicines including Zepbound and Mounjaro.



“When our Lebanon API site opens in 2027, it will be the largest API production site in U.S. history, a commitment we chose to build here, at home,” Lilly chair and CEO David A. Ricks said in the May announcement. The third project, the separately announced $4.5 billion Lilly Medicine Foundry, will develop new ways to manufacture medicines and supply drugs for clinical trials. Lilly expects the Foundry to produce its first batch of investigational medicine in 2027.
Meta projects about 300 operating jobs
Meta’s 1,500-acre campus is designed to support the company’s artificial intelligence infrastructure. The company expects more than 4,000 skilled trades workers on site at peak construction and about 300 operating jobs once the campus is complete. The late-2027 target applies to the first buildings, not the entire campus.
“This is one of our largest investments to date, and it marks an important milestone in our AI ambitions,” Rachel Peterson, Meta’s vice president of data centers, said in the February groundbreaking announcement. Meta says it will pay for the electricity, water and wastewater service its campus requires and invest more than $75 million in public water and wastewater infrastructure.
Road and water work extends beyond the sites
For drivers between Clinton and Boone counties, one visible change is the new diverging-diamond interchange at Interstate 65 and U.S. 52 near Lebanon, which is open to traffic. A separate project is realigning State Road 32 near the Meta campus and Lilly Medicine Foundry.


